p

11/12/2004 9:20 PM

OT (kinda): Highway building code question

I know, I know, alt.building.construction, but I've found that y'all
know as much about this stuff as those folks, and I feel like nobody
who reads this group would possibly have the gall to post a reply on
point unless they knew for a flat-ass outright fact what they were
talking about.

Background:
A friend of mine is working for the Army who is doing a construction
project for the Border Patrol in southern California. This project
mainly involves building box culverts, runoff slabs and road beds.
According to my buddy, these structures are built to interstate highway
specifications, even though a 5/4 ton pickup is the heaviest vehicle
these roads will probably ever see.

The Plot Thickens:
A Chief Warrant Officer (a surveyor by trade) told this crew, who was
putting in a steel rebar mat, that only every third joint be tied
together. This raised some discussion among members of the crew, one
of which swore that OSHA required that every joint be tied. This, to
me, sounds like a dumb-ass thing to say. ANSI maybe, but not OSHA.
Further, he swore that the joints could not be welded, as the welding
process weakens the steel. Also completely ridiculous as far as I can
tell, in the context of the concrete system.

I told him (my buddy) that local building codes vary (and are all
subject to the building inspector) but the only reason rebar gets tied
or welded together in a concrete system is to hold it in place until
the 'crete gets poured over it. 8 hours after the pour, that little
piece of wire has done its job. I further told him that perhaps
welding rebar may weaken the steel at that point, but does not have a
significant effect on the overall strength of the concrete system.

The Question Itself:
Is there an online (or other) resource that describes the building
codes for interstate highways? I DAGS and wound up with the UBC
(Uniform Building Code) and hundreds of places online that would sell
me a copy for about $200, but I'm not willing to pay that to prove I'm
right about this. All of my knowledge comes from old-timers and the
not-infinitesimal experiences I've had in dealing with concrete and
concrete contractors.

Thanks, y'all.

-Phil Crow


This topic has 17 replies

Dd

"DanG"

in reply to [email protected] on 11/12/2004 9:20 PM

13/12/2004 5:29 AM

Welding and cutting torches are super no-nos on reinforcing steel.
There are some cad-welding specialty end fasteners.

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
Keep the whole world singing . . . .
DanG (remove the sevens)
[email protected]



"Mark & Juanita" <[email protected]> wrote in message
news:[email protected]...
> On 11 Dec 2004 21:20:47 -0800, [email protected] wrote:
>
> ... snip
>>Background:
>>A friend of mine is working for the Army who is doing a
>>construction
>>project for the Border Patrol in southern California. This
>>project
>>mainly involves building box culverts, runoff slabs and road
>>beds.
>>According to my buddy, these structures are built to interstate
>>highway
>>specifications, even though a 5/4 ton pickup is the heaviest
>>vehicle
>>these roads will probably ever see.
>>
>
> ... our tax dollars at work.
>
>>The Plot Thickens:
>>A Chief Warrant Officer (a surveyor by trade) told this crew,
>>who was
>>putting in a steel rebar mat, that only every third joint be
>>tied
>>together. This raised some discussion among members of the
>>crew, one
>>of which swore that OSHA required that every joint be tied.
>>This, to
>>me, sounds like a dumb-ass thing to say. ANSI maybe, but not
>>OSHA.
>>Further, he swore that the joints could not be welded, as the
>>welding
>>process weakens the steel.
>
> That particular statement alone should have been enough for the
> crew to
> have told the CWO to go pound sand. The strength of weld joints
> is
> actually stronger the the steel itself. Take two plates, weld
> them
> together, place in a vise near the seam, bend back and forth --
> the steel
> will fracture away from the joint before the joint fractures
> (for a good
> weld job).
>
>
> .. more snip
>>
>>The Question Itself:
>>Is there an online (or other) resource that describes the
>>building
>>codes for interstate highways? I DAGS and wound up with the UBC
>>(Uniform Building Code) and hundreds of places online that would
>>sell
>>me a copy for about $200, but I'm not willing to pay that to
>>prove I'm
>>right about this. All of my knowledge comes from old-timers and
>>the
>>not-infinitesimal experiences I've had in dealing with concrete
>>and
>>concrete contractors.
>
> Can't help with UBC, but you might check some of the DOT web
> sites, I
> will bet that the specifications and requirements, in more
> detail than you
> would ever care to know, for interstate highway construction are
> available
> on one of their sites.
>
>>
>>Thanks, y'all.
>>
>>-Phil Crow
>

p

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 8:02 AM


Todd Fatheree wrote:
> [email protected]> wrote in message
> news:[email protected]...
> > I know, I know, alt.building.construction, but I've found that
y'all
> > know as much about this stuff as those folks, and I feel like
nobody
> > who reads this group would possibly have the gall to post a reply
on
> > point unless they knew for a flat-ass outright fact what they were
> > talking about.
>
> I'm not going to let that stop me. ;-)
>
> > Background:
> > A friend of mine is working for the Army who is doing a
construction
> > project for the Border Patrol in southern California. This project
> > mainly involves building box culverts, runoff slabs and road beds.
> > According to my buddy, these structures are built to interstate
highway
> > specifications, even though a 5/4 ton pickup is the heaviest
vehicle
> > these roads will probably ever see.
> >
> > The Plot Thickens:
> > A Chief Warrant Officer (a surveyor by trade) told this crew, who
was
> > putting in a steel rebar mat, that only every third joint be tied
> > together. This raised some discussion among members of the crew,
one
> > of which swore that OSHA required that every joint be tied. This,
to
> > me, sounds like a dumb-ass thing to say. ANSI maybe, but not OSHA.
> > Further, he swore that the joints could not be welded, as the
welding
> > process weakens the steel. Also completely ridiculous as far as I
can
> > tell, in the context of the concrete system.
>
> I don't see how OSHA would be involved, and I doubt there is an ANSI
> standard either. There may be an ACI (American Concrete Instutite)
> standard, or the DOT may have their own standard.
>
That's kinda what I was, uh, fishing for. Not ANSI specifically, but,
you know, UL or ANSI or something. That gives me a topic for a new
Google search. Thanks.

> > I told him (my buddy) that local building codes vary (and are all
> > subject to the building inspector) but the only reason rebar gets
tied
> > or welded together in a concrete system is to hold it in place
until
> > the 'crete gets poured over it. 8 hours after the pour, that
little
> > piece of wire has done its job. I further told him that perhaps
> > welding rebar may weaken the steel at that point, but does not have
a
> > significant effect on the overall strength of the concrete system.
>
> I consulted my wife who about a million years ago as a civil
engineering
> student did a summer internship with Illinois DOT inspecting road
> construction. Her recollection is that they did not tie every rebar
> intersection together. After compacting the road bed, the chairs are
put
> into place and the rebar is laid down over that. She agrees that the
only
> point to tying the rebar together is to keep them in place while the
> concrete is poured. So, tying every single intersection together
would be
> overkill. Here in the North, the rebar is epoxy-coated, so welding
would
> kinda screw that up. But where your buddy is, there may not be a
> requirement for epoxy-coated steel due to the lack of salt applied to
the
> roads.
>
> todd

Thanks, Todd. You (or your lovely wife) couldn't point me toward a
chapter and verse description in this regard, could you? My buddy is
new to construction but old to the Army, so would like to be able to
say, "Well, sir, Section 7 Paragraph 3 of the Uniform Building Code
says..."

Also, this information is for his (and mine) own personal edification.
Thanks again.

p

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 7:35 AM


Jay Pique wrote:
> [email protected] wrote:
>
> snip
> >The Plot Thickens:
> >A Chief Warrant Officer (a surveyor by trade) told this crew, who
was
> >putting in a steel rebar mat, that only every third joint be tied
> >together. This raised some discussion among members of the crew,
one
> >of which swore that OSHA required that every joint be tied. This,
to
> >me, sounds like a dumb-ass thing to say. ANSI maybe, but not OSHA.
> >Further, he swore that the joints could not be welded, as the
welding
> >process weakens the steel. Also completely ridiculous as far as I
can
> >tell, in the context of the concrete system.
> >
> >I told him (my buddy) that local building codes vary (and are all
> >subject to the building inspector) but the only reason rebar gets
tied
> >or welded together in a concrete system is to hold it in place until
> >the 'crete gets poured over it. 8 hours after the pour, that little
> >piece of wire has done its job. I further told him that perhaps
> >welding rebar may weaken the steel at that point, but does not have
a
> >significant effect on the overall strength of the concrete system.
> snip
>
> I've been pouring slabs on a rate job lately, and we only tie (most)
> corners and where the rebar sags too much. Given the relatively
light
> gauge of tie-wire I typically see used, and the relative lack of
> tightening thereof, I doubt that the ties make any structural
> difference.
>
> Were it a slab of my own, I'd tie each joint - and well.

I agree. Unless of course it were what amounts to a driveway
(light-duty occasional use) with a mat of #8 rebar 2 inches above the
bottom of the slab and a mat of #5 rebar 4 inches above that--did I
mention a 15-inch overall thickness of the slab? As you can see, this
is slightly overengineered. Interstate highway specs on a (literally)
paved Border Patrol truck path.
>
> As far as welding goes, I highly doubt a welded joint is anything
less
> than multiply stronger than the tie-wired joints. YMMV.
>
> JP

I also agree there. I think the point of the statement was that the
actual weld weakens the reinforcing rod at the joint because the heat
hardens the steel and makes it brittle (?). I'm not sure of the
(twisted) logic behind that statement.

MJ

Mark & Juanita

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 6:30 PM

On Sun, 12 Dec 2004 11:43:56 -0500, Nova <[email protected]> wrote:

>[email protected] wrote:
>
>> The Question Itself:
>> Is there an online (or other) resource that describes the building
>> codes for interstate highways? I DAGS and wound up with the UBC
>> (Uniform Building Code) and hundreds of places online that would sell
>> me a copy for about $200, but I'm not willing to pay that to prove I'm
>> right about this. All of my knowledge comes from old-timers and the
>> not-infinitesimal experiences I've had in dealing with concrete and
>> concrete contractors.
>
>The California DOT has their manuals on-line. See:
>
> http://www.dot.ca.gov/manuals.htm

That should be a pretty good resource. Given the engineering requirements
for assuring earthquake survivability, the specifications listed by the CA
DOT will probably be as stringent as one can find. The only other possibly
more stringent requirement would be for construction in areas of heavy
clay.

LJ

Larry Jaques

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 7:50 PM

On Sun, 12 Dec 2004 18:30:21 -0700, Mark & Juanita
<[email protected]> calmly ranted:

>On Sun, 12 Dec 2004 11:43:56 -0500, Nova <[email protected]> wrote:
>
>>[email protected] wrote:
>>
>>> The Question Itself:
>>> Is there an online (or other) resource that describes the building
>>> codes for interstate highways? I DAGS and wound up with the UBC
>>> (Uniform Building Code) and hundreds of places online that would sell
>>> me a copy for about $200, but I'm not willing to pay that to prove I'm
>>> right about this. All of my knowledge comes from old-timers and the
>>> not-infinitesimal experiences I've had in dealing with concrete and
>>> concrete contractors.
>>
>>The California DOT has their manuals on-line. See:
>>
>> http://www.dot.ca.gov/manuals.htm
>
> That should be a pretty good resource. Given the engineering requirements
>for assuring earthquake survivability, the specifications listed by the CA
>DOT will probably be as stringent as one can find. The only other possibly
>more stringent requirement would be for construction in areas of heavy
>clay.

There are plenty of BOTH in LoCal. My lot was a red clay pit with half
an inch of topsoil tossed on.


--
REBOOT AMERICA!
-----------------------
http://diversify.com Website Programming

Nn

Nova

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 11:43 AM

[email protected] wrote:

> The Question Itself:
> Is there an online (or other) resource that describes the building
> codes for interstate highways? I DAGS and wound up with the UBC
> (Uniform Building Code) and hundreds of places online that would sell
> me a copy for about $200, but I'm not willing to pay that to prove I'm
> right about this. All of my knowledge comes from old-timers and the
> not-infinitesimal experiences I've had in dealing with concrete and
> concrete contractors.

The California DOT has their manuals on-line. See:

http://www.dot.ca.gov/manuals.htm

--
Jack Novak
Buffalo, NY - USA
(Remove "SPAM" from email address to reply)

Td

"TeamCasa"

in reply to [email protected] on 11/12/2004 9:20 PM

13/12/2004 9:04 AM

This project
> |>mainly involves building box culverts, runoff slabs and road beds.
> |>According to my buddy, these structures are built to interstate highway
> |>specifications, even though a 5/4 ton pickup is the heaviest vehicle
> |>these roads will probably ever see.

> |>Further, he swore that the joints could not be welded, as the welding
> |>process weakens the steel.

> One reference I have at hand, "Placing Reinforcing Bars", Concrete
> Reinforcing Steel Institute, Chicago IL, 1970, states in part," The
> field welding of crossing bars should be avoided.... Tests have shown
> that this can reduce the strength of a bar to 35 to 40 percent of its
> capacity."

Only an engineer can authorize the use of weldable rebar and the weld
specifications.
It is very common to weld this type of rebar. Welding any other kind can
weaken the bar ajacent to the welds, but even non-weldable rebar can be
welded in certian circumstances.


> Here's a quick reference from a PE:
>
> http://www.k1ttt.net/technote/welding.html

From above link.
The ACI 318-99 Building Code Requirements for Structural
Concrete (which is referenced by all building codes in
the US) states:

"7.5.4 -- Welding of crossing bars shall not be
permitted for assembly of reinforcement unless
authorized by the engineer."
"R 7.5.4 -- 'Tack' welding (welding crossing bars) can
seriously weaken a bar at the point welded by creating a
metallurgical notch effect. This operation can be
performed safely only when the material welded and
welding operations are under continuous competent
control, as in the manufacture of welded wire fabric."

Dave

Pg

Patriarch

in reply to [email protected] on 11/12/2004 9:20 PM

23/12/2004 3:51 AM

>> That should be a pretty good resource. Given the engineering
>> requirements
>>for assuring earthquake survivability, the specifications listed by
>>the CA DOT will probably be as stringent as one can find. The only
>>other possibly more stringent requirement would be for construction in
>>areas of heavy clay.
>
> There are plenty of BOTH in LoCal. My lot was a red clay pit with half
> an inch of topsoil tossed on.
>

And mine is black & grey clay. But I've built the topsoil up quite a bit.
There's lots of 'byproducts' from this hobby composting behind the shed.

Patriarch

JM

John McCoy

in reply to [email protected] on 11/12/2004 9:20 PM

13/12/2004 4:39 PM

Wes Stewart <n7ws_@_yahoo.com> wrote in
news:[email protected]:

> I am not a welder, structural engineer or metallurgist, however, I've
> worked with all three and know that welding rebar is not a trivial
> exercise.

I'm under the impression that rebar is basically cast. Welding to
either cast steel or cast iron is relatively complex (gotta be
pre-heated & cooled at the correct rate, etc)...not like pointing
your wire welder at a piece of rolled plate or bar stock.

John

JP

Jay Pique

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 2:06 AM

[email protected] wrote:

snip
>The Plot Thickens:
>A Chief Warrant Officer (a surveyor by trade) told this crew, who was
>putting in a steel rebar mat, that only every third joint be tied
>together. This raised some discussion among members of the crew, one
>of which swore that OSHA required that every joint be tied. This, to
>me, sounds like a dumb-ass thing to say. ANSI maybe, but not OSHA.
>Further, he swore that the joints could not be welded, as the welding
>process weakens the steel. Also completely ridiculous as far as I can
>tell, in the context of the concrete system.
>
>I told him (my buddy) that local building codes vary (and are all
>subject to the building inspector) but the only reason rebar gets tied
>or welded together in a concrete system is to hold it in place until
>the 'crete gets poured over it. 8 hours after the pour, that little
>piece of wire has done its job. I further told him that perhaps
>welding rebar may weaken the steel at that point, but does not have a
>significant effect on the overall strength of the concrete system.
snip

I've been pouring slabs on a rate job lately, and we only tie (most)
corners and where the rebar sags too much. Given the relatively light
gauge of tie-wire I typically see used, and the relative lack of
tightening thereof, I doubt that the ties make any structural
difference.

Were it a slab of my own, I'd tie each joint - and well.

As far as welding goes, I highly doubt a welded joint is anything less
than multiply stronger than the tie-wired joints. YMMV.

JP

TF

"Todd Fatheree"

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 2:58 AM

[email protected]> wrote in message
news:[email protected]...
> I know, I know, alt.building.construction, but I've found that y'all
> know as much about this stuff as those folks, and I feel like nobody
> who reads this group would possibly have the gall to post a reply on
> point unless they knew for a flat-ass outright fact what they were
> talking about.

I'm not going to let that stop me. ;-)

> Background:
> A friend of mine is working for the Army who is doing a construction
> project for the Border Patrol in southern California. This project
> mainly involves building box culverts, runoff slabs and road beds.
> According to my buddy, these structures are built to interstate highway
> specifications, even though a 5/4 ton pickup is the heaviest vehicle
> these roads will probably ever see.
>
> The Plot Thickens:
> A Chief Warrant Officer (a surveyor by trade) told this crew, who was
> putting in a steel rebar mat, that only every third joint be tied
> together. This raised some discussion among members of the crew, one
> of which swore that OSHA required that every joint be tied. This, to
> me, sounds like a dumb-ass thing to say. ANSI maybe, but not OSHA.
> Further, he swore that the joints could not be welded, as the welding
> process weakens the steel. Also completely ridiculous as far as I can
> tell, in the context of the concrete system.

I don't see how OSHA would be involved, and I doubt there is an ANSI
standard either. There may be an ACI (American Concrete Instutite)
standard, or the DOT may have their own standard.

> I told him (my buddy) that local building codes vary (and are all
> subject to the building inspector) but the only reason rebar gets tied
> or welded together in a concrete system is to hold it in place until
> the 'crete gets poured over it. 8 hours after the pour, that little
> piece of wire has done its job. I further told him that perhaps
> welding rebar may weaken the steel at that point, but does not have a
> significant effect on the overall strength of the concrete system.

I consulted my wife who about a million years ago as a civil engineering
student did a summer internship with Illinois DOT inspecting road
construction. Her recollection is that they did not tie every rebar
intersection together. After compacting the road bed, the chairs are put
into place and the rebar is laid down over that. She agrees that the only
point to tying the rebar together is to keep them in place while the
concrete is poured. So, tying every single intersection together would be
overkill. Here in the North, the rebar is epoxy-coated, so welding would
kinda screw that up. But where your buddy is, there may not be a
requirement for epoxy-coated steel due to the lack of salt applied to the
roads.

todd

MJ

Mark & Juanita

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 6:27 PM

On 11 Dec 2004 21:20:47 -0800, [email protected] wrote:

... snip
>Background:
>A friend of mine is working for the Army who is doing a construction
>project for the Border Patrol in southern California. This project
>mainly involves building box culverts, runoff slabs and road beds.
>According to my buddy, these structures are built to interstate highway
>specifications, even though a 5/4 ton pickup is the heaviest vehicle
>these roads will probably ever see.
>

... our tax dollars at work.

>The Plot Thickens:
>A Chief Warrant Officer (a surveyor by trade) told this crew, who was
>putting in a steel rebar mat, that only every third joint be tied
>together. This raised some discussion among members of the crew, one
>of which swore that OSHA required that every joint be tied. This, to
>me, sounds like a dumb-ass thing to say. ANSI maybe, but not OSHA.
>Further, he swore that the joints could not be welded, as the welding
>process weakens the steel.

That particular statement alone should have been enough for the crew to
have told the CWO to go pound sand. The strength of weld joints is
actually stronger the the steel itself. Take two plates, weld them
together, place in a vise near the seam, bend back and forth -- the steel
will fracture away from the joint before the joint fractures (for a good
weld job).


.. more snip
>
>The Question Itself:
>Is there an online (or other) resource that describes the building
>codes for interstate highways? I DAGS and wound up with the UBC
>(Uniform Building Code) and hundreds of places online that would sell
>me a copy for about $200, but I'm not willing to pay that to prove I'm
>right about this. All of my knowledge comes from old-timers and the
>not-infinitesimal experiences I've had in dealing with concrete and
>concrete contractors.

Can't help with UBC, but you might check some of the DOT web sites, I
will bet that the specifications and requirements, in more detail than you
would ever care to know, for interstate highway construction are available
on one of their sites.

>
>Thanks, y'all.
>
>-Phil Crow

bB

[email protected] (Bob K 207)

in reply to Mark & Juanita on 12/12/2004 6:27 PM

20/12/2004 7:46 AM

>That particular statement alone should have been enough for the crew to
>have told the CWO to go pound sand. The strength of weld joints is
>actually stronger the the steel itself. Take two plates, weld them
>together, place in a vise near the seam, bend back and forth -- the steel
>will fracture away from the joint before the joint fractures (for a good
>weld job).
>
>

Actually the CWO is correct, on both comments.

Tie wire is only there to hold the rebar in place until the concrete is placed.
RC is not space shuttle work or brain surgery. Just get the correct number of
bars at the correct depth & you'll be fine.

Rebar is not to be welded unless it is a weldable grade. Most commonly used
rebar has too much carbon. If site welding of rebar cages made sense (cost or
performance) they'd be doing instead of using tie wire

cheers
Bob


MJ

Mark & Juanita

in reply to Mark & Juanita on 12/12/2004 6:27 PM

20/12/2004 7:04 PM

On 20 Dec 2004 07:46:33 GMT, [email protected] (Bob K 207) wrote:

>>That particular statement alone should have been enough for the crew to
>>have told the CWO to go pound sand. The strength of weld joints is
>>actually stronger the the steel itself. Take two plates, weld them
>>together, place in a vise near the seam, bend back and forth -- the steel
>>will fracture away from the joint before the joint fractures (for a good
>>weld job).
>>
>>
>
>Actually the CWO is correct, on both comments.
>
>Tie wire is only there to hold the rebar in place until the concrete is placed.
> RC is not space shuttle work or brain surgery. Just get the correct number of
>bars at the correct depth & you'll be fine.
>
>Rebar is not to be welded unless it is a weldable grade. Most commonly used
>rebar has too much carbon. If site welding of rebar cages made sense (cost or
>performance) they'd be doing instead of using tie wire
>
>cheers
>Bob
>
>

Yep, following the links provided by another poster, it appears that
rebar is actually weakened by welding. My bad. [slinking back to the
corner for now]

WS

Wes Stewart

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 8:17 PM

On Sun, 12 Dec 2004 18:27:33 -0700, Mark & Juanita
<[email protected]> wrote:

|On 11 Dec 2004 21:20:47 -0800, [email protected] wrote:
|
|... snip
|>Background:
|>A friend of mine is working for the Army who is doing a construction
|>project for the Border Patrol in southern California. This project
|>mainly involves building box culverts, runoff slabs and road beds.
|>According to my buddy, these structures are built to interstate highway
|>specifications, even though a 5/4 ton pickup is the heaviest vehicle
|>these roads will probably ever see.

They ought to be building a 50' high wall from San Ysidro to
Brownsville.
|>
|
|... our tax dollars at work.
|
|>The Plot Thickens:
|>A Chief Warrant Officer (a surveyor by trade) told this crew, who was
|>putting in a steel rebar mat, that only every third joint be tied
|>together. This raised some discussion among members of the crew, one
|>of which swore that OSHA required that every joint be tied. This, to
|>me, sounds like a dumb-ass thing to say. ANSI maybe, but not OSHA.
|>Further, he swore that the joints could not be welded, as the welding
|>process weakens the steel.

The Navy ought to know.
|
| That particular statement alone should have been enough for the crew to
|have told the CWO to go pound sand. The strength of weld joints is
|actually stronger the the steel itself.

Oh, please.

The discussion concerns REBAR, not steel plate. ANSI/AWS D1.4 is one
applicable standard. It is quite expensive to buy.

I am not a welder, structural engineer or metallurgist, however, I've
worked with all three and know that welding rebar is not a trivial
exercise.

One reference I have at hand, "Placing Reinforcing Bars", Concrete
Reinforcing Steel Institute, Chicago IL, 1970, states in part," The
field welding of crossing bars should be avoided.... Tests have shown
that this can reduce the strength of a bar to 35 to 40 percent of its
capacity."

For example, one of my metallurgist co-workers investigated the
results of some missile warhead testing against steel-reinforced
concrete bunker targets.

The Navy built the bunkers to be used for warhead proof of
performance. When the destruction exceeded the calculated results, it
was determined that instead of tying the rebar in a one-foot grid; the
Navy had welded the joints.

My friend showed me a one foot length of #10 rebar that looked like
the ends had been cut on a shear. The whole target area was covered
in one-foot long pieces of rebar and the sand that you wanted that CWO
to pound.

You tax dollars funded a retest at about $1M per missile.

Thank you very much.

Here's a quick reference from a PE:

http://www.k1ttt.net/technote/welding.html

JP

Jay Pique

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 6:37 PM

On 12 Dec 2004 07:35:28 -0800, [email protected] wrote:

>Jay Pique wrote:

>> Were it a slab of my own, I'd tie each joint - and well.
>
>I agree. Unless of course it were what amounts to a driveway
>(light-duty occasional use) with a mat of #8 rebar 2 inches above the
>bottom of the slab and a mat of #5 rebar 4 inches above that--did I
>mention a 15-inch overall thickness of the slab? As you can see, this
>is slightly overengineered. Interstate highway specs on a (literally)
>paved Border Patrol truck path.

Sounds like a footer for The Wall that we're going to build.

>> As far as welding goes, I highly doubt a welded joint is anything
>>less than multiply stronger than the tie-wired joints. YMMV.
>
>I also agree there. I think the point of the statement was that the
>actual weld weakens the reinforcing rod at the joint because the heat
>hardens the steel and makes it brittle (?). I'm not sure of the
>(twisted) logic behind that statement.

You're right. He's wrong. Dontcha love it!

JP

TF

"Todd Fatheree"

in reply to [email protected] on 11/12/2004 9:20 PM

12/12/2004 10:37 AM

<[email protected]> wrote in message
> Thanks, Todd. You (or your lovely wife) couldn't point me toward a
> chapter and verse description in this regard, could you? My buddy is
> new to construction but old to the Army, so would like to be able to
> say, "Well, sir, Section 7 Paragraph 3 of the Uniform Building Code
> says..."

I'm sorry, we can't. My wife's road-building career ended 15 years ago
after her internship with IDOT and she has exclusively built high-rises and
other commercial buildings since. I guess measuring concrete slump,
checking asphalt truck weight, and testing concrete cylinders had a limited
appeal. Although she did learn how to make "grader chicken". You wrap a
raw chicken up real good with aluminum foil and place it in the engine
compartment of the nearest road grader first thing in the morning. When
lunch time arrives, bon appetit. Sadly, we don't have access to a road
grader, so I've never been able to test the recipe.

todd


You’ve reached the end of replies