How are the roads that you drive on?
States Delay Highway Projects Due to Costs By KELLI KENNEDY, Associated
Press Writer
Fri Apr 7
The cost of building roads has gotten so high, not even dirt is cheap
anymore. As a result, many states are postponing scores of highway
projects.
The reconstruction work from the eight hurricanes that have hit the
United States since 2004 has combined with a rise in population in some
states to drive up the demand for labor, material and equipment. That,
in turn, has pushed up wages and prices.
Surging fuel prices, China's immense demand for concrete and steel and
the reconstruction of Iraq are also pushing U.S. road construction
costs higher.
"We plan for cost increases, but this has been a situation that a lot
of events have come together all at one time," said Lowell Clary, an
assistant secretary at the Florida Department of Transportation.
Until 2004, highway material costs nationally were fairly steady, with
a 12-year average annual increase of 1.8 percent, according to the U.S.
Bureau of Labor Stats. But those costs rose 12.5 percent in 2005, the
bureau said.
According to the bureau, hot-rolled steel bars and structures were up
45 percent in 2004 from the year before, and diesel fuel was up 27
percent. Marked increases were also reported for crushed stone,
ready-mix concrete and asphalt paving material.
In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
year, and a cubic yard of dirt climbed from $4.38 to $7.24, according
to the state Transportation Department.
"Between higher labor increases and the materials increases, we're
having to pass that on to the customer, therefore our prices are up
substantially," said Mike Horan, a paving contractor near Sarasota.
Florida has about 8,000 projects in various stages in its five-year
work program but was forced to defer 62 of them when its highway budget
came up short about $1 billion, Clary said. Seven projects were
deferred in booming Miami-Dade County.
Ricky Leme often sits in bumper-to-bumper traffic in an area where one
of the projects has been postponed.
"They should get on it now," said Leme, a process server. "This is
screwing up everybody's work. Right now it's taking about a half-hour
to get to the freeway."
Some states are finding fewer contractors are bidding on jobs, either
because they have more work than they can handle, or they cannot get
the labor or the materials they need. Fewer bids can mean higher
prices.
In Alaska, a road project that was expected to cost $6 million had only
one bid, which came in at $10 million. Only two contractors bid on a
Washington state road project in January, said Kevin Dayton, a
construction engineer for the state. The low bid was $5 million over
the engineer's estimate of $22.3 million.
To encourage more bids, Washington state is offering to give
contractors a portion of the savings for coming up with creative ideas
that reduce costs without compromising quality. California is trying to
forecast cost increases more accurately and come up with more realistic
job estimates, in the hope that will encourage more contractors to bid.
Contractors' bids are coming in well over the estimates in Georgia
because the hurricane cleanup along the Gulf Coast has made it more
difficult and costly to hire laborers, said David Graham, director of
construction for the Georgia Department of Transportation. Georgia
postponed 84 projects in 2005, Graham said.
"Equipment operators, truck drivers and laborers are getting tougher to
find," he said.
__
Associated Press Writer David Fischer contributed to this report from
Miami.
"SteveF" <[email protected]> wrote in message
news:[email protected]...
>
> "LRod" <[email protected]> wrote in message
> news:[email protected]...
> > On Sat, 8 Apr 2006 20:48:39 -0400, "SteveF" <[email protected]> wrote:
> >
> >>
> >><[email protected]> wrote in message
> >>news:[email protected]...
> >>> Excuse me, but did you quote concrete at $749 PER YARD^3 ?
> >>>
> >>>
> >>> --
> >>>
> >>> Larry Wasserman Baltimore, Maryland
> >>> [email protected]
> >>>
> >>
> >>That's what it said. Most likely Ms Kennedy doesn't know the difference
> >>between cement and concrete.
> >
> > Are you suggesting cement goes for $564-749 a yard? I don't think the
> > math works out for that in a typical six bag mix. That would be
> > roughly $90/yd for cement alone (on the low end), and the aggregate
> > and sand hasn't even been added in yet. Nor have the other rents the
> > concrete company has to account for.
> >
> > However, I'm struck by something else--there are typically 564 lbs of
> > cement in a cubic yard of concrete (six bag mix--according to the
> > website I looked at). That number looks disturbingly familiar. What
> > are the odds that some facts got mixed up somewhere?
> >
>
> I was trying a ballpark guess at how many bags of cement would go into a
> cubic yard and the cost per bag but I think you are correct and the cost
> range is still too high.
>
> Kinda' makes me wonder about the rest of the facts in the article.
>
> Steve.
>
Which brings up one of my pet peeves... Many news articles I read are
loaded with obvious factual errors, use of wrong words (allowed in place of
aloud, for example), etc. It gives the impression of very poor quality
reporting. Which, of course, leads one to suspect the reported facts that
are not so obviously in error, not only in that article, but in the entire
publication...
Jerry
LRod wrote:
> On 7 Apr 2006 21:37:11 -0700, "Too_Many_Tools"
> <[email protected]> wrote:
>
> >In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
> >year,
>
> Man, I must be out of touch. Are those prices correct? Last time I
> priced concrete (admittedly a decade ago), it was running around
> $80-100 a yard in the Chicago area. I've never priced it down here
> (FL).
>
> --
> LRod
It may be for material & labor. That would be my guess. Another reply
mentioned pure portland cement, but I think that's sold by the ton.
LRod <[email protected]> writes:
>On 7 Apr 2006 21:37:11 -0700, "Too_Many_Tools"
><[email protected]> wrote:
>>In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
>>year,
>Man, I must be out of touch. Are those prices correct? Last time I
>priced concrete (admittedly a decade ago), it was running around
>$80-100 a yard in the Chicago area. I've never priced it down here
>(FL).
The last time I bought concrete here in Minnesota was about two years ago
and it cost me around $135 for one yard. That was for one of those you
haul it type trailers of concrete. A concrete truck would probably have
been around $100 a yard if I needed more.
I've heard over the last year or two that concrete is nearly impossible
to get in Florida. Concrete suppliers won't even talk to you if you
aren't a contractor or somebody who buys concrete all the time.
Brian Elfert
On Sat, 8 Apr 2006 20:48:39 -0400, "SteveF" <[email protected]> wrote:
>
><[email protected]> wrote in message
>news:[email protected]...
>> Excuse me, but did you quote concrete at $749 PER YARD^3 ?
>>
>>
>> --
>>
>> Larry Wasserman Baltimore, Maryland
>> [email protected]
>>
>
>That's what it said. Most likely Ms Kennedy doesn't know the difference
>between cement and concrete.
Are you suggesting cement goes for $564-749 a yard? I don't think the
math works out for that in a typical six bag mix. That would be
roughly $90/yd for cement alone (on the low end), and the aggregate
and sand hasn't even been added in yet. Nor have the other rents the
concrete company has to account for.
However, I'm struck by something else--there are typically 564 lbs of
cement in a cubic yard of concrete (six bag mix--according to the
website I looked at). That number looks disturbingly familiar. What
are the odds that some facts got mixed up somewhere?
--
LRod
Master Woodbutcher and seasoned termite
Shamelessly whoring my website since 1999
http://www.woodbutcher.net
Proud participant of rec.woodworking since February, 1997
email addy de-spam-ified due to 1,000 spams per month.
If you can't figure out how to use it, I probably wouldn't
care to correspond with you anyway.
"LRod" <[email protected]> wrote in message
news:[email protected]...
> On Sat, 8 Apr 2006 20:48:39 -0400, "SteveF" <[email protected]> wrote:
>
>>
>><[email protected]> wrote in message
>>news:[email protected]...
>>> Excuse me, but did you quote concrete at $749 PER YARD^3 ?
>>>
>>>
>>> --
>>>
>>> Larry Wasserman Baltimore, Maryland
>>> [email protected]
>>>
>>
>>That's what it said. Most likely Ms Kennedy doesn't know the difference
>>between cement and concrete.
>
> Are you suggesting cement goes for $564-749 a yard? I don't think the
> math works out for that in a typical six bag mix. That would be
> roughly $90/yd for cement alone (on the low end), and the aggregate
> and sand hasn't even been added in yet. Nor have the other rents the
> concrete company has to account for.
>
> However, I'm struck by something else--there are typically 564 lbs of
> cement in a cubic yard of concrete (six bag mix--according to the
> website I looked at). That number looks disturbingly familiar. What
> are the odds that some facts got mixed up somewhere?
>
I was trying a ballpark guess at how many bags of cement would go into a
cubic yard and the cost per bag but I think you are correct and the cost
range is still too high.
Kinda' makes me wonder about the rest of the facts in the article.
Steve.
<[email protected]> wrote in message
news:[email protected]...
> Excuse me, but did you quote concrete at $749 PER YARD^3 ?
>
>
> --
>
> Larry Wasserman Baltimore, Maryland
> [email protected]
>
That's what it said. Most likely Ms Kennedy doesn't know the difference
between cement and concrete.
Steve.
On Sat, 08 Apr 2006 14:14:45 GMT, RoyJ <[email protected]> wrote:
>I suspect that the prices quoted are for bulk loads of the Portland
>Cement powder used to make the ready mixed concrete. I saw the original
>article, it was from the Associated press, written by an non technical
>jounalist.
>
Given that it was from an AP article that makes sense. Non-technical
writer but with the intent of showing how bad things are -- got to keep
that vision of a "soup-line" America going.
>LRod wrote:
>> On 7 Apr 2006 21:37:11 -0700, "Too_Many_Tools"
>> <[email protected]> wrote:
>>
>>
>>>In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
>>>year,
>>
>>
>> Man, I must be out of touch. Are those prices correct? Last time I
>> priced concrete (admittedly a decade ago), it was running around
>> $80-100 a yard in the Chicago area. I've never priced it down here
>> (FL).
>>
+--------------------------------------------------------------------------------+
If you're gonna be dumb, you better be tough
+--------------------------------------------------------------------------------+
"LRod" <[email protected]> wrote in message
news:[email protected]...
> On 7 Apr 2006 21:37:11 -0700, "Too_Many_Tools"
> <[email protected]> wrote:
>
>>In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
>>year,
>
> Man, I must be out of touch. Are those prices correct? Last time I
> priced concrete (admittedly a decade ago), it was running around
> $80-100 a yard in the Chicago area. I've never priced it down here
> (FL).
>
Different grade, produced on site by prevailing wage people who, though
well-paid and a half, are getting scarcer.
Why this should be is a mystery, given the wages and the way of life. Up
here, seems particularly suited for a young man - work your tail off for
six, seven months, earning the equivalent of nearly two year's wages for
your peers, then go ski. By the time you're older, you drive and supervise.
Perhaps it's that "work your tail off" part that scares them away.
And the water weighs?
"RoyJ" <[email protected]> wrote in message
news:[email protected]...
> Specific gravity of 'standard' (I presume type 1A) portland cement is 3.15
> That works out to 5443 pounds per yard. 6 bag mix is based on 94 pound
> bags or 564 pounds of Portland cement per cubic yard of concrete. Figure
> around 11% of the concrete is Portland cement, rest is aggregate.
> Aggregate in quantity runs low single digit $ per ton so most of the
> material cost for concrete is in the Portland cement.
>
> Portland cement cost is highly driven by fuel. It costs money to run the
> kiln, it costs money to transport the product to the ready mix plant.
>
> LRod wrote:
>> On Sat, 8 Apr 2006 20:48:39 -0400, "SteveF" <[email protected]> wrote:
>>
>>
>>><[email protected]> wrote in message
>>>news:[email protected]...
>>>
>>>>Excuse me, but did you quote concrete at $749 PER YARD^3 ?
>>>>
>>>>
>>>>--
>>>>
>>>> Larry Wasserman Baltimore, Maryland
>>>> [email protected]
>>>>
>>>
>>>That's what it said. Most likely Ms Kennedy doesn't know the difference
>>>between cement and concrete.
>>
>>
>> Are you suggesting cement goes for $564-749 a yard? I don't think the
>> math works out for that in a typical six bag mix. That would be
>> roughly $90/yd for cement alone (on the low end), and the aggregate
>> and sand hasn't even been added in yet. Nor have the other rents the
>> concrete company has to account for.
>>
>> However, I'm struck by something else--there are typically 564 lbs of
>> cement in a cubic yard of concrete (six bag mix--according to the
>> website I looked at). That number looks disturbingly familiar. What
>> are the odds that some facts got mixed up somewhere?
>>
<[email protected]> wrote in message
news:[email protected]...
>
> LRod wrote:
>> On 7 Apr 2006 21:37:11 -0700, "Too_Many_Tools"
>> <[email protected]> wrote:
>>
>> >In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
>> >year,
>>
>> Man, I must be out of touch. Are those prices correct? Last time I
>> priced concrete (admittedly a decade ago), it was running around
>> $80-100 a yard in the Chicago area. I've never priced it down here
>> (FL).
>>
>> --
>> LRod
>
> It may be for material & labor. That would be my guess. Another reply
> mentioned pure portland cement, but I think that's sold by the ton.
>
Cement can be bought by the bag. When I bought a truck load of concrete
blocks I *thought* I ordered bags of mortar mix and they delivered bags of
cement. Luckily the local concrete company let me buy a trailer load of
sand so the masons could make mortar.
Steve.
Specific gravity of 'standard' (I presume type 1A) portland cement is
3.15 That works out to 5443 pounds per yard. 6 bag mix is based on 94
pound bags or 564 pounds of Portland cement per cubic yard of concrete.
Figure around 11% of the concrete is Portland cement, rest is aggregate.
Aggregate in quantity runs low single digit $ per ton so most of the
material cost for concrete is in the Portland cement.
Portland cement cost is highly driven by fuel. It costs money to run the
kiln, it costs money to transport the product to the ready mix plant.
LRod wrote:
> On Sat, 8 Apr 2006 20:48:39 -0400, "SteveF" <[email protected]> wrote:
>
>
>><[email protected]> wrote in message
>>news:[email protected]...
>>
>>>Excuse me, but did you quote concrete at $749 PER YARD^3 ?
>>>
>>>
>>>--
>>>
>>> Larry Wasserman Baltimore, Maryland
>>> [email protected]
>>>
>>
>>That's what it said. Most likely Ms Kennedy doesn't know the difference
>>between cement and concrete.
>
>
> Are you suggesting cement goes for $564-749 a yard? I don't think the
> math works out for that in a typical six bag mix. That would be
> roughly $90/yd for cement alone (on the low end), and the aggregate
> and sand hasn't even been added in yet. Nor have the other rents the
> concrete company has to account for.
>
> However, I'm struck by something else--there are typically 564 lbs of
> cement in a cubic yard of concrete (six bag mix--according to the
> website I looked at). That number looks disturbingly familiar. What
> are the odds that some facts got mixed up somewhere?
>
>
michael <[email protected]> wrote in
news:[email protected]:
> Too_Many_Tools wrote:
>
> Memory may be hazy, but ISTR that several years ago a couple test
> stretches of hiway were paved with a mix that included old ground-up
> tires in the asphalt and/or concrete. The reason this practice wasn't
> used widely was that the surface lasted much longer which meant less
> labor was needed over the long term. Texas had one of the test hiways
> IIRC.
>
> buckshot
>
California did a section of freeway in Oakland that way last fall. It's
shot, now. One of the worst in the area, after 4 to 6 months. Much worse
than before they started. I don't remember what went wrong, but something
certainly did.
Patriarch
Excuse me, but did you quote concrete at $749 PER YARD^3 ?
--
Larry Wasserman Baltimore, Maryland
[email protected]
Too_Many_Tools wrote:
Memory may be hazy, but ISTR that several years ago a couple test
stretches of hiway were paved with a mix that included old ground-up
tires in the asphalt and/or concrete. The reason this practice wasn't
used widely was that the surface lasted much longer which meant less
labor was needed over the long term. Texas had one of the test hiways IIRC.
buckshot
> How are the roads that you drive on?
>
>
> States Delay Highway Projects Due to Costs By KELLI KENNEDY, Associated
> Press Writer
> Fri Apr 7
>
>
> The cost of building roads has gotten so high, not even dirt is cheap
> anymore. As a result, many states are postponing scores of highway
> projects.
>
> The reconstruction work from the eight hurricanes that have hit the
> United States since 2004 has combined with a rise in population in some
> states to drive up the demand for labor, material and equipment. That,
> in turn, has pushed up wages and prices.
>
> Surging fuel prices, China's immense demand for concrete and steel and
> the reconstruction of Iraq are also pushing U.S. road construction
> costs higher.
>
> "We plan for cost increases, but this has been a situation that a lot
> of events have come together all at one time," said Lowell Clary, an
> assistant secretary at the Florida Department of Transportation.
>
> Until 2004, highway material costs nationally were fairly steady, with
> a 12-year average annual increase of 1.8 percent, according to the U.S.
> Bureau of Labor Stats. But those costs rose 12.5 percent in 2005, the
> bureau said.
>
> According to the bureau, hot-rolled steel bars and structures were up
> 45 percent in 2004 from the year before, and diesel fuel was up 27
> percent. Marked increases were also reported for crushed stone,
> ready-mix concrete and asphalt paving material.
>
> In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
> year, and a cubic yard of dirt climbed from $4.38 to $7.24, according
> to the state Transportation Department.
>
> "Between higher labor increases and the materials increases, we're
> having to pass that on to the customer, therefore our prices are up
> substantially," said Mike Horan, a paving contractor near Sarasota.
>
> Florida has about 8,000 projects in various stages in its five-year
> work program but was forced to defer 62 of them when its highway budget
> came up short about $1 billion, Clary said. Seven projects were
> deferred in booming Miami-Dade County.
>
> Ricky Leme often sits in bumper-to-bumper traffic in an area where one
> of the projects has been postponed.
>
> "They should get on it now," said Leme, a process server. "This is
> screwing up everybody's work. Right now it's taking about a half-hour
> to get to the freeway."
>
> Some states are finding fewer contractors are bidding on jobs, either
> because they have more work than they can handle, or they cannot get
> the labor or the materials they need. Fewer bids can mean higher
> prices.
>
> In Alaska, a road project that was expected to cost $6 million had only
> one bid, which came in at $10 million. Only two contractors bid on a
> Washington state road project in January, said Kevin Dayton, a
> construction engineer for the state. The low bid was $5 million over
> the engineer's estimate of $22.3 million.
>
> To encourage more bids, Washington state is offering to give
> contractors a portion of the savings for coming up with creative ideas
> that reduce costs without compromising quality. California is trying to
> forecast cost increases more accurately and come up with more realistic
> job estimates, in the hope that will encourage more contractors to bid.
>
> Contractors' bids are coming in well over the estimates in Georgia
> because the hurricane cleanup along the Gulf Coast has made it more
> difficult and costly to hire laborers, said David Graham, director of
> construction for the Georgia Department of Transportation. Georgia
> postponed 84 projects in 2005, Graham said.
>
> "Equipment operators, truck drivers and laborers are getting tougher to
> find," he said.
>
> __
>
> Associated Press Writer David Fischer contributed to this report from
> Miami.
>
On 7 Apr 2006 21:37:11 -0700, "Too_Many_Tools"
<[email protected]> wrote:
>In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
>year,
Man, I must be out of touch. Are those prices correct? Last time I
priced concrete (admittedly a decade ago), it was running around
$80-100 a yard in the Chicago area. I've never priced it down here
(FL).
--
LRod
Master Woodbutcher and seasoned termite
Shamelessly whoring my website since 1999
http://www.woodbutcher.net
Proud participant of rec.woodworking since February, 1997
email addy de-spam-ified due to 1,000 spams per month.
If you can't figure out how to use it, I probably wouldn't
care to correspond with you anyway.
> Which brings up one of my pet peeves... Many news articles I read are
> loaded with obvious factual errors, use of wrong words (allowed in place
> of
> aloud, for example), etc. It gives the impression of very poor quality
> reporting. Which, of course, leads one to suspect the reported facts that
> are not so obviously in error, not only in that article, but in the entire
> publication...
>
I find that whenever I am reading an article about a topic in which I am
knowledgeable, they always have it wrong. So that does make me very
suspicious about those articles that are on topics I am naive about. Of
course, the exception to this is the Wall Street Journal...
"LRod" <[email protected]> wrote in message
news:[email protected]...
> On 7 Apr 2006 21:37:11 -0700, "Too_Many_Tools"
> <[email protected]> wrote:
>
>>In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
>>year,
>
> Man, I must be out of touch. Are those prices correct? Last time I
> priced concrete (admittedly a decade ago), it was running around
> $80-100 a yard in the Chicago area. I've never priced it down here
> (FL).
>
> --
> LRod
>
> Master Woodbutcher and seasoned termite
>
> Shamelessly whoring my website since 1999
>
> http://www.woodbutcher.net
>
The concrete for my shop floor in December was $105 per yard and that
included surcharges for the calcium chloride and extra cement for 4500 PSI.
When I did another shop 3 years ago it was $90.
Steve.
central North Carolina
In article <[email protected]>,
"Jerry Foster" <[email protected]> wrote:
> Which brings up one of my pet peeves... Many news articles I read are
> loaded with obvious factual errors, use of wrong words (allowed in place of
> aloud, for example), etc. It gives the impression of very poor quality
> reporting. Which, of course, leads one to suspect the reported facts that
> are not so obviously in error, not only in that article, but in the entire
> publication...
>
> Jerry
Which describes the main reason I'm _not_ working in journalism,
effectively "wasting" several years' work. Disillusionment occurs very
quickly when one hears the "professors" making egregious factual errors
when "teaching" about various news subjects. Worse, they would not deign
to even look at the accurate, or even just opposing, information when
directed to it.
Firearms and drug issues were the most glaring of the error-riddled
speeches*, but construction methods, failure modes in machinery, and
economic issues followed closely behind. Law Enforcement, i.e Police,
reporting classes were simply a waste of good time and professors'
oxygen.
*Yep, speeches. (When not outright screeds) There was nothing being
taught but the professors' personal biases, in classes which were
supposed to teach students how such subjects should be approached by
professional reporters.
Spend a lifetime some week reading a book called: "Interpretative
Reporting." It propounds the doctrine that reporting should not only
tell the traditional Five "Ws," but also why the readers should care. To
be fair, it does mention even-handed reporting, in one sentence.
When advocating only mere even-handedness became reproachable, I left,
three credit hours short of my B.S. and with 4 job offers. (But I
couldn't buy into the B.S. of the other kind. (Stupid bull-headedness on
my part, but that's the way it was. :)
I suspect that the prices quoted are for bulk loads of the Portland
Cement powder used to make the ready mixed concrete. I saw the original
article, it was from the Associated press, written by an non technical
jounalist.
LRod wrote:
> On 7 Apr 2006 21:37:11 -0700, "Too_Many_Tools"
> <[email protected]> wrote:
>
>
>>In Florida, concrete went from $564 a cubic yard in 2004 to $749 last
>>year,
>
>
> Man, I must be out of touch. Are those prices correct? Last time I
> priced concrete (admittedly a decade ago), it was running around
> $80-100 a yard in the Chicago area. I've never priced it down here
> (FL).
>
On Sun, 09 Apr 2006 04:34:30 +0100, LRod <[email protected]>
wrote:
>On Sat, 8 Apr 2006 20:48:39 -0400, "SteveF" <[email protected]> wrote:
>><[email protected]> wrote in message
>>news:[email protected]...
>>> Excuse me, but did you quote concrete at $749 PER YARD^3 ?
>>
>>That's what it said. Most likely Ms Kennedy doesn't know the difference
>>between cement and concrete.
>
>Are you suggesting cement goes for $564-749 a yard? I don't think the
>math works out for that in a typical six bag mix. That would be
>roughly $90/yd for cement alone (on the low end), and the aggregate
>and sand hasn't even been added in yet. Nor have the other rents the
>concrete company has to account for.
>
>However, I'm struck by something else--there are typically 564 lbs of
>cement in a cubic yard of concrete (six bag mix--according to the
>website I looked at). That number looks disturbingly familiar. What
>are the odds that some facts got mixed up somewhere?
That, or they could be quoting a total price for the job of repaving
a stretch of road - where you take the costs of the raw materials and
add in all the labor hours /at/ /prevailing/-/wage/ /rates/ for the
site prep, surveying and layout, base mix and compaction, form work,
placing, sawing stress relief joint lines, finishing and cleanup,
striping and reflectors, signs and traffic signals, etc.
--<< Bruce >>--
--
Bruce L. Bergman, Woodland Hills (Los Angeles) CA - Desktop
Electrician for Westend Electric - CA726700
5737 Kanan Rd. #359, Agoura CA 91301 (818) 889-9545
Spamtrapped address: Remove the python and the invalid, and use a net.